THE DEVELOPMENT OF A PROJECT MANAGEMENT PLAN FOR THE IMPLEMENTATION OF THE SIERRA WORKFORCE SOLUTION TIME MANAGEMENT SYSTEM PROJECT AT THE ANTIGUA PUBLIC UTILITIES AUTHORITY

 

 

EXECUTIVE SUMMARY

The Antigua Public Utilities Authority is one, if not only, the largest employer in Antigua and Barbuda. With a staff complement of over eight hundred employees working across more than ten locations, management of its prime resource was a costly challenge.

 Numerous attempts were made to encourage employees to be honest about time paid for time worked. However, this was easier said than done. Buddy punching was an issue, and even after implementing a biometric software to improve productivity and accuracy in the payroll, it was later revealed that this software was not compatible with the current payroll system.

As a result, employees recorded their work times in books and time sheets. This posed a monthly challenge for the Payroll and Accounts Department who were tasked with processing salaries and wages on time.

Therefore, this document will describe the development of the Project Management Plan for the implementation of the Sierra Workforce Solutions Time Management Software Software at the Antigua Public Utilities Authority.

This will be necessary for accurate and efficient time management of the Authority’s staff complement. The general objective was to develop a Project Management Plan according to the Project Management Institute's (PMI) standards and framework to successfully manage the implementation of the Sierra Workforce Time Management System Project at the Antigua Public Utilities Authority.

 The specific objectives were: (1) To create the project charter that formally authorizes the project, and to gives the pProject mManager the authority to use/utilize resources within the Antigua Public Utilities Authority to prepare the Project Management Plan;

(2) To develop a project management plan to define how the project will be initiated, planned, monitored and controlled, and closed;

(3) To create a Scope Management Plan to ensure that all the work, and only the work required is done according to the plan, and to ensure the successful completion of the project;

(4) To create a Time Management Plan to ensure that all work is completed within time constraints;

(5) To create a Cost Management Plan to plan, manage and control the project's budget;

(6) To create a Quality Management Plan to identify quality requirements in order to ensure deliverables meet expectations;

(7) To develop a Resource Management Plan to ensure that all resources are identified and managed efficiently for the successful completion of the project;

(8) To develop a Communications Management plan to ensure the timely, accurate and effective communication to all stakeholders;

(9) To create a Risk Management Plan to identify and examine risks and create responses and management to these risks to ensure the successful completion of the project;

(10) To develop a Procurement Management plan to ensure the correct products, services and results are procured by the project; and

(11) To create a stakeholder management plan to identify and manage all project stakeholders’ expectations and to ensure efficient and effective stakeholder engagement throughout the life of the project.

The research methodology for the Final Graduation Project was analytical and observational. To add, both primary and secondary sources of information were utilized for data collection and analysis.

Wherein the main sources used to gather information included A Guide to Project Management Body of Knowledge (PMBOK Guide) Sixth Edition, PMI’s online resources, interviews and meetings that were held with key stakeholders within the organization and the time management software development company.

Consequently, the information was analyzed to create each subsidiary plan used to develop the Project Management Plan for the implementation of the Sierra Workforce Solutions Time Management Software System at the Authority.

Hence, the development of the Project Management Plan for the Sierra Workforce Solutions Time Management Software Project will cover all project knowledge areas. Moreover, this is the first attempt to the creation of a robust and comprehensive Project Management Plan for any project within the Antigua Public Utilities Authority and will form part of the Authority’s overall strategic objective in realizing business value from future projects, by documenting and leading projects successfully according to the plan.

Lastly, it will be extremely important for the Authority to establish a Project Management Office to support the various Business Units with their project’s efforts.

This office will provide Project Manaement Training to the Engineers/Project Managers and their Teams with a focus on successfully managing projects within the Authority. Also, implementing a change control process, which is overseen by a Change Control Board will be critical for ensuring all projects are managed efficiently and effectively, and that any changes to any aspect of the project is approved (or denied) before being implemented. Also, project communication is key for ensuring all stakeholders are kept abreast of the project’s performance, and it is the Project Manager’s responsibility to ensure that information is communicated at the right time, to the right persons and via right medium. Properly documented meeting minutes with action points can assist the Project Manager with communicating the project’s status to all stakeholders and inform project team members of their assigned tasks to be completed. Finally, the creating of a lessons learned repository would be ideal for use as a reference for future projects.

Descargar Aquí:

https://www.uci.ac.cr/Biblioteca/Tesis/PFGMAP2133.pdf

Estudiante: NICOLE D. EDWARDS

Fecha de aprobación: abril 2021

Tutor: JAMES PEREZ

Lector: CARLOS BRENES MENA

Lector: XAVIER SALAS